Substation Projects
Navigation



Duke Energy
  • Upgraded entire substation, Phillips Plant Substation, 2012
  • Installed new feeder position, Cassadaga Substation, 2012
  • Upgraded bus and instrument transformers, Desoto City Substation, 2012
  • Installed new distribution breaker, switches and neutral reactors, Clearwater Substation, 2012
  • Installed new 230kV switches, breakers, 1590acsr strain bus Holopaw Substation, 2011-12
  • Install 3 69KV towers & switches, breaker, & Reconfiguration Bus, Bronson Substation, 2011
  • Installed new transformer and switchgear, Welch Road Substation, 2011
  • Replaced 230 kV breaker and switches, Rio Pinar Substation, 2011
  • Install Bank Electrical Project, Central Plaza Substation, 2011
  • Constructed new switch yard, Chiefland Substation, 2011
  • Replacement of 230KV breakers and switches, Holopaw Substation 2011
  • Removed 115KV Substation Bartow Power Plant, 2011
  • Electrical Construction, Bayridge Substation, 2010
  • 230KV Electrical Construction, Woodsmere Substation, 2011
  • Electrical Construction, Kam Services, 51st Street Substation, 2008
  • Electrical Construction, Kam Services, Ocala, 2007

Lee County Electrical Cooperative, LCEC
  • Installation of upgrades Carnestown Substation 2011
  • Civil Construction Del Prado Substation, 2010
  • Current Transformer Installation all Substations in LCEC system, 2010
  • Civil Construction Carnestown Substation, 2009
  • Civil Construction Lee Substation, 2009
  • Civil and Electrical Construction Industrial Substation, 2008
  • Oil Breaker Replacment, System Wide, 2006 - 2007
  • Electrical Construction, North Cape Substation, 2007
  • Civil and Electrical Construction, Lee Substation, 2007
  • Built Portable Substation, All Phase Electric, 2006
  • Electrical Construction, North Cape Substation, 2005

Florida Power and Light, FPL
  • Transformer testing, Waukesha, West County, 2012
  • Regasketing and maintenance on 500KVA transformer, Waukesha, Martin Plant, 2012
  • Electrical Construction, Waukesha, Various Substation, 2007

Other Utilities
  • Sumter Electric Coop, Rebuild Rainbow Lakes Substation, Dunnellon
  • City of Wauchula/DOE -┬áCivil and Electrical Substation Construction and Turn Key Relay Vault, 2010